(gentle music) Let's explore how to monitor the risks you've identified, the life cycle of project risks, and how often you should reevaluate your risks. Once a risk has been identified and assessed, and triggers identified, the risk is assigned to a risk owner. The risk owner is a team member with an intimate knowledge of the risk and its triggers. As part of the handoff from project manager to risk owner, there needs to be communication about how and when to escalate or deescalate the risk to the project owner. The most obvious need for communication is whenever a risk trigger has occurred. The risk owners should notify the project manager immediately, so the risk response plan can be initiated. If there is no risk response plan, then it's time to develop one quickly. The risk owner may help their project manager with this task. The second communication is when the risk owner feels the risk priority or impact have changed. The escalation process could go one of two ways. If the risk owner feels there's immediate danger, or if they feel the change pushed a low priority risk into the high priority range, the risk owner can notify the project manager immediately. However, if there is no imminent danger, the risk owner can flag the risk to be reviewed as part of the next risk review meeting. As in most parts of a project, risks are fluid throughout the project life cycle, such that the project manager must monitor from the start of the project to its close out. Here are a few process related items the project manager can implement to help them manage this process. When identifying risks, be sure to identify a phase of the project where they have the highest likelihood of being triggered. It's important to keep a risk proximity list of items that are low priority, but that have a high likelihood of occurring in the near term. Keep the risk registry up to date at all times, so every team member has a real-time view of the project risks. And finally, follow the plan. In the beginning of your project, you defined what the risk management plan would be, along with how you would manage risk. Follow the plan you put in place. The same goes for risk response plans. If a trigger occurs, initiate the risk response plan you have in place. Don't deviate just because it may be a false alarm. Trust the process.